Update on our Building Project
A lot has happened on our site since the last update. At the end of 2024, the area was filled with around 80 cubic meters of sand - a necessary…
A lot has happened on our site since the last update. At the end of 2024, the area was filled with around 80 cubic meters of sand - a necessary…
Last week, we donated some of our school desks to three likeminded schools in the community [St. Nicolas, Miklin School and a sister school]. These desks allow two occupants use…
Some progress has also been made on the construction site. The sanitary building particular has undergone major development. First of all, the wooden door frames were installed and the staircase…
We have made some progress on our construction site in the last few months! At the beginning of July, the foundation of the ground floor, i.e. the ceiling of our…
The construction of our school is making progress.A lot has happened in the last few weeks. The floor has been poured with about 70 m³ of concrete and our construction…
Our school takes shape! The concrete dried up successfully and the ground got firm. Unfortunately we had to take a building break during December because we were out of funds.…